Request
comes after PHSMA allowed the compressor station to recommence operations
before the causes of recent unplanned natural gas releases were definitively
identified and resolved
Washington (December 14,
2020) – Senators Edward J. Markey (D-Mass.) and Elizabeth Warren (D-Mass.)
wrote to the Pipeline and Hazardous Materials Safety Administration (PHMSA)
opposing its decision to authorize Enbridge, Inc. to restart operations at the
Weymouth compressor station after activities were halted following two recent
emergency shutdowns. On November 25, 2020, PHMSA issued its approval of
Enbridge’s “Weymouth Station Restart Plan” without having reviewed a complete
third-party investigation of station safety or the findings of a finished Root
Cause Failure Analysis. In the letter, the senators also raised concerns over
PHMSA’s decision to accede to Enbridge’s requests to limit the list of
corrective actions the company had to take to address hazardous conditions.
Despite the remaining questions regarding the cause of the unplanned shutdowns
and uncertainties about the compressor station’s safety, PHMSA allowed the
Weymouth compressor station to recommence operations on December 4, 2020.
“PHMSA should ensure that
all necessary corrective actions are identified and taken before the
facility is permitted to restart, not after the compressor station yet
again exposes the community to danger,” write the Senators in
their letter to PHMSA. “Before PHMSA makes any future decisions about
operations at the station, we urge you to revoke your approval of the restart
plan, allow for the completion of a Root Cause Failure Analysis, and review the
results of a thorough investigation into the causes of the two unplanned
emergency shutdowns.”
A copy of the letter can
be found
HERE.
Today’s letter follow a
series of actions taken by Senators Markey and Warren to urge responsible
entities to shut down the Weymouth compressor station. On November 9, 2020,
Senators Markey and Warren wrote to the
Federal
Energy Regulatory Commission (FERC) in support of a petition requesting a
rehearing and rescission of the In-Service Authorization issued for the natural
gas compressor station in Weymouth, Massachusetts on September 24, 2020. On
September 30, 2020, the Senators wrote to the
PHMSA,
urging the Administration to halt activities at the Weymouth compressor station
and investigate the station’s safety following an equipment failure and
emergency shutdown earlier that month. The next day, Enbridge agreed to
pause
start of operations at the gas compressor station. In July, Senator
Markey and Senator Warren sent a letter to the
Massachusetts
Department of Environmental Protection, urging the Department to require
that Algonquin Gas Transmission immediately halt ongoing venting of natural gas
at the meter stations located at the Calpine Fore River Energy Center site and
the Weymouth compressor station. The Senators also wrote to
FERC to
request that the Commission rescind the notice to proceed on construction of
the compressor station, due to the lack of complete permits. In April, Senators
Warren and Markey
wrote
to Enbridge, Inc. calling for public health and safety protections at the
Weymouth compressor construction site as they continued construction during the
coronavirus pandemic.
Last year, Senators
Warren and Markey
introduced legislation
that would block construction of any compressor station built as part of a
pipeline project to export natural gas – as the Weymouth station would, with
plans to export natural gas to Canada. The Senators, along with Rep. Stephen F.
Lynch (MA-08), also sent a letter to the Chief Executive Officer of Enbridge,
Inc.
expressing
serious concerns about the company’s proposal to construct the
compressor station in Weymouth.